COMANCO’s team continues to battle the forces of nature at a power plant in North Florida to keep the project on track.
In the past weeks, rain has caused several lost days and re-work, but this is not dampening the spirits of the team. Superintendent Bill Newman assisted by Foremen Chris Sullivan, Pedro Pedraza and Leadman Jose Martinez are leading their teammates on all three fronts, the Effluent Processing Facility (EPF), North West Ditch (NWD) and Pond 7 (P7). In this period, they have installed the precast concrete pump station, welded and tested several large diameter pipes and excavated the formation for NWD and P7 amongst other works. Great job to the entire COMANCO crew!
SAFETY ★ QUALITY ★ SERVICE