Starting this week the COMANCO crew installed 6 Pre-Cast concrete Energy Dissipater structures at a landfill in Miami, Florida.
These concrete Energy Dissipaters weigh about 30,000 lbs (15 Tons) each. Due to limited road access and existing powerlines, the use of a crane to place these structures was not possible. Superintendent, Chase Yarbrough, and the project team deliberated on other possibilities for installing these structures & came up with a plan to execute this task.
Additionally, another one of COMANCO’s projects had to perform a similar task 1 week prior, and potential hazards, safety topics/concerns, and learning experiences were effectively relayed to this crew to help make this particular activity safe & successful too.
All around there was great communication & teamwork by COMANCO as a whole!