Over the past few weeks, a COMANCO team has worked on multiple tasks on a stormwater improvement project in Palatka, FL.

The crew is nearing completion pouring a 6-inch concrete slab over a 1-acre EPF basin. They will start installing three centrifugal pumps at the basin’s pump station in the coming weeks. The crew’s progress grading and prepping the perimeter stormwater ditch and pond has also gained momentum, as liner installation is scheduled to start next week.

Keep up the great work team!