• X
CORPORATE OFFICE 813-988-8829 | ELKO OFFICE 775-778-9577   APPLY NOW

COMANCO Completes 11.5 Acre Landfill Expansion Project

by

COMANCO has completed an 11.5 acre landfill expansion project in Central Florida this week.  The project finished on time and in accordance with COMANCO’s safety, quality, and service expectations and ideals.

The earthwork crews arrived onsite August, 2014 and worked all the way through the new year to completion. The scope of the earthwork crews’ work consisted of de-mucking all areas in and around the new cell limits, removing and installing reinforced concrete pipe and fabriform, gradation of the new cell’s subgrade and storm water ditches, installation of the leachate collection HDPE pipe, gravel, manhole and grading of the sand cover and turn-around pad on top of the 6 layer liner system.

Pic22

The Liner crew arrived onsite October, 2014 and finished installing the 6 layer leachate collection system by December. The scope of the liner crew’s work consisted of installing the 2 layers of GCL, 60mil Geomembrane, and Geocomposite on top of the subgrade, and installing the primary and secondary sump collection boxes and pipe boots.

The crews, led by Superintendents Bill Newman and Arnulfo Martinez, Foreman Matt Carroll, Project Manager Dan McRae and Project Engineer Craig Stevenson did an excellent job of delivering a great project while ensuring no safety incidents.

Pic21 Pic23 Pic24