• X
CORPORATE OFFICE 813-988-8829 | ELKO OFFICE 775-778-9577   APPLY NOW

Work Progresses at Central Florida Liner Installation Site

by
  • 01-COMANCO-Riverview-Blog.png
  • 02-COMANCO-Riverview-Blog.png
  • 03-COMANCO-Riverview-Blog.png
  • 04-COMANCO-Riverview-Blog.png
  • 05-COMANCO-Riverview-Blog.png

Work Progresses at Central Florida Liner Installation Site Following Hurricane Ian. 

Project Manager Marcelo Santos says the team at one of our Central Florida Liner Installation Sites is concluding the needed repairs due to the storm damage so that they can resume wind ballast and liner installation.

Despite the recent weather, COMANCO Superintendents Gerardo Ruiz and Jorge Gomez have been focusing their crew on the safest means of production as they install liner on the ditches and slopes of this water collection project. 

Our team will install approximately 74 Acres of liner by the end of this project, which is currently 78% complete with 3,230,00 SF of liner in place. COMANCO is proud of our crew’s dedication to providing Safety, Quality, and Service on all our job sites.  

 

SAFETY ★ QUALITY ★ SERVICE
________________________________________________________________________

COMANCO is an environmental, commercial, and civil construction company specializing in the construction of containment facilities and the nation’s leading service provider to the geosynthetics marketplace. 

Each year our experienced crews, most with more than five years of service with COMANCO, install over 100 million square feet of geosynthetics at project sites across the nation. Do your next project the right way, “The COMANCO Way,” because your business and our reputation depend on it. Discover our services or get a quote on your next project today.

LinkedIn Facebook Instagram |Twitter YouTube