COMANCO Making Progress on New Landfill Cell

  • JED-CELL-14-UPDATE-Blog-frame-2.jpg
  • JED-CELL-14-UPDATE-Blog-frame-1.jpg
  • JED-CELL-14-UPDATE-Blog-frame-3.jpg
  • JED-CELL-14-UPDATE-Blog-frame-4.jpg
  • JED-CELL-14-UPDATE-Blog-frame-5.jpg

COMANCO is finishing the installation of a geosynthetic liner system for a new 18-acre landfill cell in Osceola County.

The crew has successfully installed geosynthetic clay liner (GCL), two layers of 60mil textured HDPE geomembrane, and two layers of geocomposite.

All that remains is finishing the tie-in at the sump and installing the rain flaps on the slopes.

Superintendent Gerardo Ruiz and his crew are working hard to complete the project safely and on time.