COMANCO Making Progress at Chemical Plant in Central FL

by

Superintendents Jeremy Giles and Larry Graham lead the earthwork and liner crews to complete the 40-acres of cut/fill and subgrade and the installation of 40-acres of 60 mil liner, stabilization and gravel drains.

For Phase I of the project, they have currently completed the subgrade and are working to complete 60 mil liner installation and the installation of the gravel drain. The estimated completion time for the entire project is early June 2020.

Great job to the entire COMANCO Team!