COMANCO Completing Disc Harrow Project
The COMANCO team is wrapping up a small disc harrow project on a chemical plant in Florida today. The crew is using an 850 dozer with a disc harrow to disc a 1-acre area on a gyp stack where sod …
The COMANCO team is wrapping up a small disc harrow project on a chemical plant in Florida today. The crew is using an 850 dozer with a disc harrow to disc a 1-acre area on a gyp stack where sod …
Below are a couple of pictures from a cooling pond liner install on a chemical plant in Florida being led by Project Supervisor Max Macedo. The crew has lined over 30 acres of smooth and textured 40 mil HDPE geomembrane. …
COMANCO has completed the repair of a wastewater treatment facility in Northern California. The 60mil smooth HDPE was cut to examine the subgrade beneath the liner. Superintendent Carlos Garcia and crew did an excellent job in patching the liner despite steep and …
COMANCO has completed repairs of a chemical pond at a gold mine located in Northern Nevada. The crew replaced a section of liner that was previously damaged and installed numerous 80mil Double Sided Textured HDPE patches within the pond. The crew was led by …
The COMANCO team recently finished up the earthwork on a spray field pond project at a chemical plant in Florida. The crew mobilized for a second time on this project this month to install road base, grade out swales, install …
COMANCO made repairs on a liner system of a landfill near central Florida last week. The crew arrived onsite to excavate 2′ into the protective cover soil and investigate suspect areas on the closed landfill. After they exposed the buried liner, the crew found …
COMANCO is continuing the geosynthetics installation on the Boyette Road Reservoir in Wesley Chapel, Florida. The work is currently 40% complete which consists of a 60 mil HDPE Textured Geomembrane, Non-Woven Textile, Composite Drainage Net, and Geosynthetic Clay Liner. The team …
This year, the 2015 SWANA Landfill Gas & Biogas Symposium is being held at the Sheraton Hotel in New Orleans, LA from March 16th – 19th. The World’s Premier Forum on Landfill Gas and Biogas Utilization & Technology The 38th …
COMANCO recently completed work installing secondary containment liner for a chemical plant in Central Florida. The crew, led by Gerardo Ruiz, utilized a combination of polylock embed and batten bar to attach the HDPE liner to the surrounding concrete prior …
COMANCO has successfully completed the heap leach pad for a gold mine 45 minutes south of Reno, Nevada. The project included installing over 170,000 square feet of Bentomat Geosynthetic Clay Liner (GCL) & 80-mil Double Sided Textured High Density Polyethylene (HDPE) …