The COMANCO crew is coming down to the end of a 155 acre liner installation on a Cooling Pond Closure prjoect at a local Florida chemical plant. Also progressing is the gyp stack slope closure on the same site with a slope drain installation. The crew will have installed 800 LF of the drain by the end of the week and will continue with header pipe installation (13,500 LF total of HDPE pipe). Crews are being led by Project Superintendent Gary Mitchell and Project Foreman Max Macedo.