COMANCO Completes Wastewater Reservoir Geosynthetic Installation in Florida

by

COMANCO recently finished up with the current installation of the Boyette Reservoir in Wesley Chapel, Florida. COMANCO’s scope of work is approximately 95% complete with all work onsite which consists of the supply and installation of all geosynthetics for the slopes (60 mil HDPE Textured Liner, Geosynthetic Clay Liner, Composite Drainage Net, and two applications of Non-Woven Textile). The total slope area is just shy of 20 acres. The crew will remobilize in May to close up the liner system 100% once all work inside of the liner limits is completed.

P1020722

The crew has done a great job, worked hard and stayed positive throughout entire construction thus far, kept safety as the # 1 priority, and maintained on schedule for our valued customer. The crew has been led by foreman Nathan Wilfong. Enjoy some progress photos!

IMG_7266 IMG_7324 IMG_7381  P1020719 P1020714