Update on Central Florida Gypsum Stack Projects

by

COMANCO is continuing to make progress on multiple projects at a Central Florida Chemical facility. The two crews led by Superintendent Gary Mitchell Jr and Supervisor Justino Macedo are constructing a Freshwater Detention Pond and installing a Supplemental Drainage System. The Detention Pond crew is prepping for the final Fabriform installation and will be looking to make a push for project completion in the coming weeks. The Supplemental Drains crew is nearly three-quarters of the way complete installing a 12-inch HDPE curtain drain and will then continue on to the lower 6-inch HDPE geocomposite drain. Both crews are working safely on their respective projects.