Rain Cap Liner Maintenance and Stormwater Improvements

by

COMANCO recently completed a stormwater collection improvements and rain cap maintenance project in Florida. The duration of the project lasted 3 months and finished with zero safety incidents. Work completed consisted of inspecting and repairing damage to the existing liner over two landfill capped cells, tying and staging tires for ballast, and re-grading of a stormwater swale and lining with 60 mil HDPE geomembrane to allow fresh water to flow. The team performed very well from start and finish. Great job to all employees involved, and thank you for the hard work and dedication to safety!

IMG_9882 IMG_1604 IMG_1650 IMG_1132 IMG_1647 IMG_1602 IMG_1601