North Florida Update

by

COMANCO and Trader Construction remain hard at work on a project in North Florida. In the last month, over 150,000 cubic yards of material has been dewatered, excavated, hauled, and compacted to create a rim dike. Other recent progress includes hauling dirt to create a new perimeter dike, and clearing / grubbing a borrow area. A minor milestone was reached earlier this week, as liner offloading was completed. All 1,000 rolls of the 60-mil textured liner have now been delivered, and it was done safely and efficiently. Stay tuned for more updates on this 250 acre earthwork, drain, and liner project.