COMANCO and Trader Construction remain hard at work on a project in North Florida. The dredge work in the first area of the pond was completed, and the cell is currently being dewatered. Although the dredge was able to remove most of the saturated material, there is a small amount remaining. Trader is currently working on removing this excess material, and placing sand tailings for the new subgrade. Once the subgrade has been established and graded, COMANCO will mobilize and complete the liner and drain installation. The dredge has moved onto the second cell. Upon completion, Trader/COMANCO will move into this cell and continue the subgrade preparation activities.