New River Regional Landfill Cell 6 Expansion Moving Along

by

COMANCO Environmental Corporation is nearing the end of the Cell 6 Expansion at New River Regional Landfill located in Union County, Florida.  The team, led by Luis Espinal (Superintendent) and Troy Watral (Project Manager), began construction on July 11th.  The on-site crew of 10 men are currently in the final week of the geosynthetic installation which consisted of deploying four layers: two layers of geocomposite and two layers of textured, high-density polyethylene (HDPE) geomembrane.  With the protective cover installation following close behind, a completion date is on schedule for the first week of September. 

 

Dsc_2097aDsc_2094aDscn0810Dscn0815Dscn0856