• X
CORPORATE OFFICE 813-988-8829 | ELKO OFFICE 775-778-9577   APPLY NOW

Live From The Field Guantanamo Bay

  • 01-LFTF-Guantanamo-03.21.2022-BLOG.jpg
  • 02-LFTF-Guantanamo-03.21.2022-BLOG.jpg
  • 03-LFTF-Guantanamo-03.21.2022-BLOG.jpg
  • 04-LFTF-Guantanamo-03.21.2022-BLOG.jpg
  • 05-LFTF-Guantanamo-03.21.2022-BLOG.jpg

Superintendent Martin Calderon is “Live From The Field” with a real-time update on the progress made on the first solid waste landfill in Guantanamo Bay, Cuba! The work continues on the 11.5-acre landfill cell as the crew moves forward to install the three-layer geosynthetic system consisting of GCL, 60mil HDPE Textured Geomembrane, and a 300mil Double-Sided Composite.

The COMANCO Team continues battling the high winds but is making progress as they work to complete the project on time!

SAFETY ★ QUALITY ★ SERVICE