Gyp Stack Supplemental Drainage System Update

by

COMANCO is nearing the halfway point of installing a 12-inch corrugated perforated HDPE drain at a Central Florida chemical facility. Led by Supervisor Jeremy Giles and Foreman Justino Macedo, the crew has installed nearly 3,000LF of the 12-inch drain. COMANCO is working safely by utilizing a professionally engineered fall protection system while working around the 17-ft deep trench. After completion of the 12-inch drain, a 6-inch geocomposite drain will then be installed. Continue to check back in as COMANCO makes progress on the drainage systems!