A COMANCO crew, led by Superintendent Charlie Ingle, is making progress on a gyp stack slope closure project at a chemical plant in Central Florida. The crew is installing a 2,000′ long drain system with 8″ HDPE pipe buried at the toe. Grading work is also taking place to prepare for geocomposite and HDPE liner installation along the 15 acre site. Work is set to finish early April.