• X
CORPORATE OFFICE 813-988-8829 | ELKO OFFICE 775-778-9577   APPLY NOW

Gyp Stack Closure at Chemical Plant

by

The side slope closure of a chemical plant gyp stack in Florida is progressing smoothly.  The crew, led by Project Superintendent Gary Mitchell, is laying 24″ header pipe, 48″ manholes, and a 12″ corrugated drain system around the NW corner and North side of the stack.

72 73 74 75 71 76