Earlier this week, COMANCO Environmental commenced construction on the 2nd phase of a 2-part Dredge Basin Liner Containment project. Installation of a new 40-mil HDPE geomembrane liner began on a 2nd 15-acre holding basin in Melbourne, FL. Superintendent, Jorge Barrantes, and a 10-man crew returned to site where they completed the 1st 660,000 SF basin & 215,000 SF clarifying pond earlier this year. The team picked up where they left off and are working safely and diligently to finish by the end of this month.