COMANCO Environmental has recently begun the second mobilization of a gypsum stack lining project at a phosphate mine in Southern Idaho. The project consists of nearly 400,000 SF of single-sided textured 60-mil HDPE geomembrane, 2.25 million SF of double-sided textured 60-mil HDPE geomembrane, and 35,000 LF of geocomposite vent strips. To date, the crew has installed over 1.8 million SF of geomembrane and 20,000 SF of geocomposite vent strips.
The 13 man crew is led by Superintendent Arnulfo Martinez and Project Manager Dan Ward. We look forward to seeing the continued progress on this project as it moves closer to completion. Keep up the great work!