COMANCO Reaches Completion Of Landfill Cell In Southern California

by

The 12-man COMANCO crew led by Superintendent, Larry Graham, have completed the installation of the first four layers of a geosynthetic five-layered system on an 8.8-acre landfill cell expansion project in Southern California. The crew has managed to install over 384,945 SF of 40-mil Double-sided Textured HDPE Liner; 384,215 SF of Reinforced GCL; 384,215 SF of 60-mil Double-sided Super Gripnet HDPE Liner; 412,131 SF of 16 oz. Non-Woven Geotextile. Over 385,131 SF of the fifth layer 8 oz. Non-Woven Geotextile will be installed over a one-foot layer of crushed rock placed over the first four layers installed for the cell.

The COMANCO crew continues to uphold safe work manner by taking proper breaks to allow our employees to stay cool and properly hydrated, so they can continue to provide the excellent service and quality our customers have come to know.