COMANCO Moving Forward at Southern California Landfill

by

COMANCO is continuing deployment of a multi-layer geosynthetic installation at a landfill in Sylmar, California. The project consists of installing 30mil HDPE geomembrane, 40mil HDPE geomembrane, 60mil HDPE geomembrane, 80mil HDPE geomembrane, GCL, 16oz geotextile, and 250mil double sided geocomposite. This complex installation has as many as eight layers of geosynthetics in multiple locations. The crew has installed over 750,000 SF of geosynthetics so far. Superintendent Tony Sanchez and crew are working on 2:1 slopes in heavily congested areas but have taken extensive measures to maintain a safe work environment. The crew is moving forward with COMANCO’s values of SAFETY ★ QUALITY ★ SERVICE. Keep up the great work team!IMG_2045 IMG_2047 IMG_2055  IMG_2075 IMG_2214 IMG_2216 IMG_2227IMG_2229 IMG_2288