COMANCO Environmental is moving along on a 30-acre C & D Landfill closure project in Plymouth, FL. A 40-mil HDPE geomembrane is being deployed over a prepared sub-grade with a geocomposite drainage layer going over the top. Superintendent, Jorge Barrantes, and a 10-man crew are working diligently and safely while progressing. 2’ of protective cover soil is being placed on top of the liner system to help maintain its integrity.