COMANCO Finishing Cooling Pond Project in Florida

by

A Cooling Pond site remediation and containment liner project is progressing well this week after being delayed due to heavy rains on a chemical plant closure in Florida.  The crew has deployed 150 out of the 160 acres of HDPE liner so far in the area.  This project began in February 2015 and the crew is working to finish the last little bit by mid-December.  The crew is being led by Foreman Max Macedo.