COMANCO Crew Deploying at Cooling Pond

The COMANCO crew continues to beat productions on a Cooling Pond Liner project in Central Florida.  So far, 40 acres of the 160 acre ponds are lined, marking 25% of the project complete.  This week, the crew has been putting the exposed edge of liner in a ballast trench in order to prevent uplift from the wind. So far, all destruct tests have passed.