COMANCO Begins Phase 2 at Plant in Central Florida

by

COMANCO recently began the second phase on a power plant in Central Florida.  The first phase completed in October 2014.  The second phase is scheduled to complete in January 2015.  The scope of work consists of installing 15 mil Gundseal, 30 mil Gundseal, 80 mil white HDPE textured liner, 80 mil white HDPE smooth liner and a Composite Drainage Net. The total area to be lined with the system is about 30 acres.

IMG_2749

The crew has done a great job in staying safe and working hard to meet the schedule demands.  The crew is led by superintendent Jorge Barrantes. Please enjoy some progress photos from this week of Phase 2.