The storage pond outside of Edmonton, Alberta, Canada, consists of 60.5 acres with 2,632,693 sqft of 60mil textured HDPE Geomembrane, 30,000 linear feet of Geocomposite gas venting beneath the pond liner, and 40,000 UV ballast bags installed on top of the liner.
The crew led by Superintendent Arnulfo Martinez, Foreman Estevan Saenz, and Leadman Ramon Irizarry went the extra mile to provide quality service in a timely manner. This crew completed 60.5 acres of exposed pond liner in under seven weeks. The crew was on-site 8/5 and started installing the liner on 8/11. With zero safety incidents, Arnulfo and his crew completed the project by 9/24.
The COMANCO team’s quality work is essential to the protection of the environment and preservation of surrounding natural resources.
COMANCO is an environmental, commercial, and civil construction company specializing in the construction of containment facilities and the nation’s leading service provider to the geosynthetics marketplace.