The COMANCO Team is working very efficiently at the Calamus Fish
Hatchery Project. So efficiently, in fact, that the project is now
scheduled to finish at the end of August, a full month ahead of
schedule!
of 51 ponds completed).
The current work for each pond includes: 1. Cleaning ponds
2. Removing old geosynthetics
3. Re-grading ponds
4. Relining ponds with new geosynthetics (Firestone EPDM)
5. Installing Mud Rock on Major roads
6. Installing Gravel on Non-Major roads
7. Harvesting sod on site and placing it around completed ponds 8. Excavating and backfilling anchor trenches Great job, team!