• X
CORPORATE OFFICE 813-988-8829 | ELKO OFFICE 775-778-9577   APPLY NOW

Freeport McMoRan Bagdad Flood Basin Liner Repair Complete

by

COMANCO completed repairing stress cracks on a pond in Bagdad, AZ. Placed approx 185 LF of cap strips over the cracks along with multiple patches & beads to repair the liner. Employees were required to tie-off while on the slope due to the pond being active and the current level.

Project was completed without incident while adhering to MSHA regulations and site specific requirements. Project was run by Foreman Pablo Gomez Medina. Great Job!

Bagdad_flood_basin_1-31-13_007Bagdad_flood_basin_1-31-13_011Bagdad_flood_basin_1-31-13_013Bagdad_flood_basin_1-31-13_026Bagdad_flood_basin_1-31-13_035Bagdad_flood_basin_1-31-13_044Bagdad_flood_basin_1-31-13_046Bagdad_flood_basin_1-31-13_047Bagdad_flood_basin_1-31-13_059Bagdad_flood_basin_1-31-13_060