COMANCO Begins Construction at Cayuga Station Cell 2

by

COMANCO team has begun construction on Cayuga Station Cell 2, located in Cayuga Indiana. This project led by superintendent Jorge Barrantes started on Wednesday, 6/6/12. The scope of the project consists of installing 660,000 square feet of 30 mil Polyvinyl Chloride (PVC), 660,000 square feet of 10 oz & 16 oz Nonwoven Geotextile in the cell and 56,000 square feet of 45 mil Reinforced Polypropylene Geomembrane (RPP) at the perimeter ditch. The 30 mil PVC installation has commenced with the  10 oz and  16 oz Nonwoven Geotextiles to follow. The team is working hard, safe and efficient to complete this project on time. Below are some pictures showing the progress that the team has made.

PanoramaPanorama_1