Deployment has started for a pond and channel lining project near Pocatello, Idaho. The COMANCO crew led by Superintendent Arnulfo Martinez and Project Engineer Nick Rauh, includes installing over 350,000 SF of 60-mil Textured High Density polyethylene (HDPE) geomembrane in a pond and over 10,000 SF in a channel. In the pond they are also installing over 110,000 SF of 8 ounce Non-Woven Geotextile, over 75,000 SF installation of 200-mil (8 ounce) DS Geocomposite, and 24″ pipe boot.
The crew has already deployed a third of the project through rainy conditions with no accidents or incidents. Thanks for the great job Arnulfo, Nick and crew!