COMANCO continues to make progress on a cooling pond earth work project at a chemical plant in Central Florida. Currently, COMANCO is more than halfway complete repairing a crack on a gyp stack. This is in addition to road improvements around the job site which will support continued improvements. They have completed the construction of soil plugs which ensure the protection of the surrounding environment for the duration of the project. The six man team, under the direction of superintendent Bill Newman, continues to compact soil and position material for construction of an energy dissipation pad in the following weeks.