The COMANCO team, working on a gyp stack closure project at a chemical plant in Florida, has completed a 24″ HDPE outlet pipe installation through a berm using directional drilling. After a few days spent preparing for this installation, the pipe was installed in about an hour. This pipe line is part of a 13,500 LF header pipe system going around the gyp stack and this particular outlet ties into an existing pipe system.