With the ramping up of crew sizes, Superintendents Jorge Barrantes and Chase Yarbrough, lead the COMANCO team to safely & efficiently complete the installation of three out of five layers of Geosynthetics (GCL, Geomembrane, and Geocomposite) in Cell 5A.
Prior to finishing up the installation of these three layers, the crew excavated anchor trench and exposed the previous Cell 4’s liner system to tie into.
To date, over 1,000,000 SF of Geosynthetics have been installed. Onsite Project Engineer, Andrew Hooks, commented, “With SAFETY, teamwork (liner crew and earthwork crew) and a lot of hard work we have been able to get a great deal of quality work completed for our customer.”
SAFETY ★ QUALITY ★ SERVICE