• X
CORPORATE OFFICE 813-988-8829 | ELKO OFFICE 775-778-9577   APPLY NOW

COMANCO Begins Work at a Central California Landfill

by

COMANCO Environmental is well underway on the liner installation at a Central California Landfill. We started the project on Monday 7/7/14 and with current productions being achieved, we anticipate a completion date of 7/16/14. Finishing in 8-9 working days on a 15 day project schedule. The project is approximately 500,000 SF of 60 mil Double-Sided Textured HDPE liner and 12oz Non-Woven Geotextile on top. Superintendent Martin Calderon and an eleven man crew are doing a great job while maintaining safety and quality. In just two days the crew has deployed over 350,000 SF of the primary liner in hot and windy conditions. The Project Manager is Scott Harker with Project Engineers Chris Washa and Nick Rauh. We look forward to completing this project safely and ahead of schedule. Keep up the great work guys!