Atheron WWTF Project is Well Underway

by

COMANCO is well underway on the Atherton WWTF project   and the crew is steadily working on completing the two Pond Liners and batten bar installation. The project consist of installing approximately 90,625 SF of 60mil HDPE textured liner in two ponds and batten bar at the concrete structures. Although we have experienced some wet weather the crew is remaining resilient and is eager to complete the project on time. The crew is led by Superintendent Juan Gomez, Project Manager Scott Harker and Project Engineer Ruben Rios-Llamas. Keep up the good work Juan!