The COMANCO crew at a Florida chemical plant is continuing the closure of a gyp stack and the lining of cooling ponds. On the gyp stack closure side, preparations are being made for a directional driller to assist with the installaition of some 24” outlet HDPE pipe into an earthen berm, and the 8th 48” manhole is being prepared to be put in place. On the cooling pond side, the crew has just crossed the 100 acre mark of total area lined out of 155 acres for this project.