• X
CORPORATE OFFICE 813-988-8829 | ELKO OFFICE 775-778-9577   APPLY NOW

COMANCO Begins Install at Coal Ash Landfill Expansion

by
Ouc_stanton_energy_01_5-24-12

COMANCO is starting work on the installation of a four layer geosynthetic material system as a part of the coal ash landfill expansion for the OUC Stanton Energy Center in Orlando, FL.  Project Superintendent Tony Sanchez will lead the crew and install the following:

Secondary Layer:                             1,253,737 SF of 60mil Textured HDPE Liner

Leak Detection Layer:                    450,835 SF of 200mil Geonet and 802,905 SF of 250mil DS Geocomposite

Primary Layer:                                   1,253,737 SF of 60mil Textured HDPE Liner with an additional 349,505 SF on an existing slope

Leachate Collection Layer:           450,835 SF of 275mil Geocomposite and 1,152,410 SF of 300mil DS Geocomposite