Over the last several months, COMANCO has been hard at work on a central Florida landfill expansion project. Superintendent Matt Carroll and Supervisor Justino Macedo are leading the charge for the earthwork crew as they continue to haul and place what will be 43,000 cubic yards of protective over the liner containment system. Following the protective cover installation, is a small crew lead by Supervisor Gerardo Ruiz installing 6-inch HDPE perforated leachate collection pipe. This collection pipe is being covered with 700 tons of drainage gravel and wrapped with geotextile for filtering. Over the next week, the crew will look to finish the leachate collection pipework and begin installing storm water structures and piping. With multiple activities happening throughout the project, COMANCO will strive to put safety at the forefront and complete this project incident free!