Yesterday, COMANCO Environmental attended a project kick-off meeting at the Seminole Electric site in Palatka, FL. COMANCO has been contracted to perform a 5-acre cell expansion to the existing Coal Ash Landfill.
Safety, project team, schedule, scope of work and budget were some of the key topics discussed followed by a site visit to the proposed expansion area and borrow pit. Ardaman & Associates will be the Engineer of Record for this project.
Project Managers Clayton Lung & Scott Harker and Project Engineer Thomas Raab were in attendance for COMANCO. Earlier this year, COMANCO completed the Stage IIA vertical expansion at the same site. COMANCO is always honored and takes pride in working for our repeat customer Seminole Electric.