Polk County North Central Landfill Phase III Gas System – Update

The COMANCO crew has been working hard on the Polk County Landfill Phase III Gas System and has now finished all 8 of the horizontal gas collectors on the North Cell of the project. The crew installed approximately 5,000 linear feet of solid and perforated 6” HDPE pipe and covered it with gravel, geotextile, and soil fill. The crew is now working on the 18” header and 2” forcemain/air supply lines that will eventually connect the collector pipes into the blower/flare system (to be installed next month).

The crew recently was rewarded with a safety lunch buffet for zero lost-time incidents on the project so far. The lunch was attended by the entire crew along with the management team and a representative each from safety, human resources, and Jones Edmunds and Associates.

Below are some progress photos.