West Contra LTS Progress Update

Uncategorized
by

Progress continues to be made at the West Contra Costa Sanitary Landfill project in Richmond, California. The crew has been busy the past 2 months with plumbing work, pump relocation, concrete pouring and forming, and electrical work.

To date, COMANCO has installed over 5,000 feet of PVC flow lines, hundreds of pipe fittings, over 140 ball valves, 45 check valves, and over 30 pump motors ranging in size from 1/10 to 5 hp with a flow capacity of over 100 gallons per minute (gpm)!

In addition, COMANCO’s electrical subcontractor has installed over 10,000 feet (and counting) of electrical wiring for this project.

The project remains on schedule and within budget parameters.