Reservoir Liner Installation

by

COMANCO recently completed the concrete ramp liner tie-in and an expansion joint liner cap at the Control Structure on the Boyette Reservoir in Pasco County, FL. All Quality Control was completed during the work. Destructive tests were sent to a 3rd party for laboratory results and non-destructive testing was performed in the field (spark testing, air test, and vacuum box testing). The engineer was onsite to inspect all testing of the liner. The concrete structure was welded up the walls using OSHA approved scaffolding. The team was led by foreman Jorge Gomez. Great job to all our employees for completing this work on schedule and with zero safety incidents!

IMG_0856 IMG_0860 IMG_0862 KIMG0075 KIMG0084