New Landfill Cell In Progress

Uncategorized
by

COMANCO crew, lead by superintendent Luis Esipnal, continues geosynthetics installation at the JED Landfill in St. Cloud, Florida.  The crew is on schedule to complete the installation of 500,000 square feet of GCL and over one million square feet of 60 mil HDPE liner and Geocomposite.