COMANCO: Liner Installation Wraps Up on Pond Renovation Project

by

COMANCO was able to complete the liner installation phase on a pond renovation project in Central Florida within the past couple of days. Supervisor Gerardo Ruiz led the 10-man crew as they installed 15 acres of 80mil HDPE textured liner and 3 acres of 200mil double sided geocomposite for gas venting under the liner system. Despite battling the end of Florida rainy season the crew was able to complete the project ahead of schedule and under budget. Most importantly COMANCO finished this incident-free which stands out the most for a valued customer. EXCELLENT WORK!