Headway Being Made on Spillway Improvement Project

by

Over the past several weeks COMANCO has been working on a spillway improvement project at a Central Florida chemical facility. Superintendents Scott Hall, Jeremy Giles and their respective crews are working together simultaneously to tackle this project. Backfilling over an abandoned spillway has recently been completed leaving only re-vegetation until the Southwest portion is wrapped up. Currently, the crews are working on grading a new storm water swale that will include multiple HDPE outlet drains and refurbishing an existing 36-inch CMP spillway. Check back in the coming weeks as this project picks up steam.