COMANCO Gets Underway with Geosynthetics Installation in South Carolina

by

The COMANCO team began deploying geosynthetics at Three Rivers Regional Landfill in Aiken, South Carolina this week.  As a three-cell landfill expansion project, the scope of work includes the supply and installation of geosynthetic clay liner (GCL), 60-mil textured HDPE geomembrane, 200-mil double-sided geocomposite and 16 oz/sy non-woven geotextile.  Additional HDPE leachate collection piping will be installed as well.  The 12-man field crew, led by Superintendent Tony Sanchez, is scheduled to finish in mid-February.  Below are progress photos showing the GCL and 60-mil geomembrane deployment.

Three_rivers_31Three_rivers_07Three_rivers_09Three_rivers_02Three_rivers_01