COMANCO Completes C & D Landfill Closure in Central FL

COMANCO Environmental recently completed construction of a 27-acre C & D Landfill closure project in Plymouth, FL.  A 40-mil HDPE geomembrane was deployed over a prepared sub-grade with a geocomposite drainage layer placed over top.

COMANCO performed earthwork and pipe operations, in addition, the geosynthetics.  With the help of GPS dozers, 2’ of protective cover soil was spread over top of the liner system to help maintain its integrity.  Nearly 2,500 LF of 6” HDPE ADS toe drain was installed around the perimeter of the closure as well.  Compliments to Supervisors, Jorge Barrantes & Kenny Frazier, and their 10-man crew on completing another quality project safely and on time.

SAFETY ★ QUALITY ★ SERVICE