Casper Regional Landfill Cell 1 & 2 Expansion

Uncategorized
by

COMANCO started on time for the geosynthetics installation on the Casper Regional Landfill. The Crew started the deployment of GCL and 60 mil Textured Liner on the slopes. This project scheduled for 20 working days and will be complete on 11/9/11. Project team is Jose Hernandez is the Supt. with his 12 man crew.

The project consist of the installation 60 mil HDPE D/S Textured Liner, 60 mil HDPE Smooth Liner, Reinforced GCL and tie in welding to the existing cell.